WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN JULY?

As the sun shines over Somerset, there will be a focus on site to progress the earthworks. This means removing and transporting topsoil and involves lorries traversing the site for the foreseeable future. You will also continue to see drainage basins being...
WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN JUNE?

This month you can expect to see more tangible progress on site, with the first of the timber frames going up. With so much of the work to date focusing on readying the site for construction, this is an obvious sign that housebuilding is well and truly underway...
WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN MAY?

This month, work to create the new junction connecting the development to the A38 will begin, however this stage only involves preparatory work within the development itself. This is a major piece of infrastructure for the development – and more details will...
WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN APRIL?

We are continuing to create the ‘spine road’ that will be the main arterial road that eventually runs from the top to the bottom of Orchard Grove, and the first section of tarmac will be laid this month. Another new road, looping around the first homes by...
WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN MARCH?

As we head into Spring and milder weather, earthworks will ramp up to make the most of drier days. This means you will see a lot more soil exposed and machinery transporting earth around the site. Our work will continue on the drainage needed for the spine road that...
WHAT’S HAPPENING ON SITE IN JULY?

WHAT’S HAPPENING ON SITE IN FEBRUARY?

This month sees the continuation of work to prepare the site, with more cut and fill earthworks taking place as the weather allows.   An exciting step forward, this month Taylor Wimpey arrives on site, so you can expect to see more contractors, new flags and...