WHAT’S HAPPENING ON SITE IN AUGUST 2023?

WHAT’S HAPPENING ON SITE IN AUGUST 2023?

This August Orchard Grove will look a little different, with a new site traffic entrance and new hoardings installed. The new hoardings will be one of the first things you see on approaching Orchard Grove and will feature graphics that give an insight into the new...
WHAT’S HAPPENING ON SITE IN AUGUST 2023?

WHAT’S HAPPENING ON SITE IN JULY 2023?

More work will take place at the Pocket Park this month, with the footpaths completed and the grass areas seeded – all ahead of the play equipment being installed. Our commercial area will begin to look different this month, as the groundworks compound will up sticks...
WHAT’S HAPPENING ON SITE IN NOVEMBER AND DECEMBER?

WHAT’S HAPPENING ON SITE IN OCTOBER?

The first sales information centre and show homes have opened at Orchard Grove, so the public can now visit part of the site for the first time. The Taylor Wimpey sales office is open and appointments need to be booked in advance. Access is via the site entrance,...
WHAT’S HAPPENING ON SITE IN NOVEMBER AND DECEMBER?

WHAT’S HAPPENING ON SITE IN FEBRUARY?

This month sees the continuation of work to prepare the site, with more cut and fill earthworks taking place as the weather allows.   An exciting step forward, this month Taylor Wimpey arrives on site, so you can expect to see more contractors, new flags and...