Now that the land for the primary school has been transferred to Somerset County Council, site set up will take place to enable work to start soon on this exciting project. This month, essential services linking to the school are also expected to be installed. 

We hope the weather this month will prove drier than April, and allow us to press ahead with work to create the new footpaths in the Pocket Park. More seeding and planting will then take place.

Elsewhere on site, a new turning head will be created for the road connecting to the pumping station, and a second culvert crossing over the tributary stream will be installed.