by admin | Jun 1, 2022 | Monthly updates
A busy month as the sun shines and helps the team make great strides on site. This June, the Galmington stream culvert will be installed, work to create the pumping station will near its completion, and earthworks will carry on across the site. Elsewhere, the spine...
by admin | May 17, 2022 | Monthly updates
This month sees a lot more vital infrastructure work take place on site. This is the final stage of the pumping station construction, with work including infilling the pump chamber; installation of services, electronics and communication channels; and...
by admin | Apr 6, 2022 | Monthly updates
This month marks the completion of the A38 junction work. We will have a new route in and out of Orchard Grove, enabling its future residents to easily access the local area. Thank you to those who have used the A38 during the work – we appreciate your patience...
by admin | Mar 8, 2022 | Monthly updates
Work to finish the new junction linking the development to the A38 is drawing to a close. This month sees the finishing touches and inspections being made, followed by the new roundabout officially opening. The Vistry sales office is set to open to the public, this...
by admin | Feb 17, 2022 | Monthly updates, News, Planning
Those living locally to the Orchard Grove development are likely to be aware that a pumping station is being built. This is a facility that safely transfers foul drainage away from the site, and is necessary to support the new homes being built. It has been designed...
by admin | Feb 17, 2022 | Monthly updates
This month sees even more progress with vital infrastructure work; the essential elements needed to make the new community function well from the start. This includes work on the new roundabout to the A38, which is now reaching its final stage. On site, work to...